Buying an HSIIDC industrial plot on transfer — the checklist

Under EMP-2015 chapter 8, every transfer needs HSIIDC's prior written permission; the Estate Manager issues a Provisional Transfer Letter within 30 days.

5 min readChecked on 28 Nov 2026

What it is

Industrial plots in HSIIDC estates are allotted freehold, but with conditions. The allottee must set up the approved project within a fixed time. The rules are in HSIIDC's Estate Management Procedures, 2015 (EMP-2015), chapter 8, as amended to 31 December 2025.

EMP-2015 treats each of these as a transfer:

  • A sale deed, an agreement to transfer later, or a power of attorney (except to family members).
  • A change of 51% or more of the stake in a firm, LLP or company.
  • A change of the largest shareholders and management in a listed company.
  • A merger or takeover where majority control passes.

Every transfer, first or later, needs prior written permission of HSIIDC.

When you need it

  • Before paying token money for an HSIIDC plot or shed.
  • Before buying the shares of a company that owns one.
  • Before taking a plot on lease. Leasing has its own chapter 7 rules.

Documents

From the seller:

  • Regular Letter of Allotment (RLA), re-allotment letters for each earlier transfer, and the allotment agreement.
  • Conveyance deed in the seller's favour.
  • Proof that the full price, including enhanced cost, is paid.
  • No-dues for maintenance, water and sewer charges, EDC and extension fees.
  • Approved building plan and occupation certificate, if built.
  • HSIIDC's acceptance of project completion, if claimed.
  • For a company: board resolution, shareholding records and MCA filings.

Steps

  1. Ask the Estate Office. EMP-2015 says the buyer must check transferability and the dues payable before any agreement. The information is available at HSIIDC's estate offices.
  2. Check eligibility for the first transfer. The original allottee must have paid the full price, including enhanced cost, and have the conveyance deed; have obtained the occupation certificate and completed the project; and have no dues outstanding.
  3. If the project is not complete, a general-category plot can still be transferred after full payment and conveyance deed, on a higher fee (step 7). A prestigious-category plot can be transferred only after the project is complete, apart from the 2023 regularisation scale.
  4. Check the category. Plots allotted under NRI or PWD categories on or after 22 August 2019 can go only to NRI or PWD buyers. Since March 2023, a PWD plot can move to general category after the project is complete, on 2% of the current reserve price or RLA rate, whichever is higher.
  5. Apply to HSIIDC. The application is made by the allottee or authorised partner or director, with the transfer or processing fee.
  6. Provisional Transfer Letter. The Estate Manager checks the application within 7 working days and issues a PTL within 30 days. A deficient application is returned with reasons within 15 working days.
  7. Comply within 120 days. Seller and buyer meet the PTL conditions within 120 days. The sale deed is registered at the Sub-Registrar. That registration date is the effective date of transfer.
  8. Re-allotment. HSIIDC signs an agreement with the buyer and issues the re-allotment letter. Building violations are recorded at inspection and regularised or undertaken before the final transfer letter.

Usual time and cost

Time. The EMP sets 7 working days to check, 30 days to issue the PTL, and 120 days to comply.

Normal transfer fee (clause 8.7), per sq m of plot area, plus GST:

  • Category A estates: Rs 300 (approx. Rs 251 per sq yd).
  • Category B: Rs 150. Category C: Rs 50.

Category A includes the HSIIDC estates at Gurugram, Manesar, Bawal, Dharuhera, Faridabad, Bahadurgarh and others.

Vacant or unbuilt general-category plots: for allotments under EMP-2015, the first transfer costs 2% of the current allotment price or double the normal fee, whichever is higher. For allotments made before EMP-2015, it is 10%.

No fee, only processing fee: transfer after the project is complete with no dues; inheritance, will or family; death; bank takeover; a later transfer after a completed-project first transfer; and EMP-2015 general allotments after completion and conveyance deed.

Interest at 12% a year is added to the transfer fee from the effective date of transfer (from the date of the request where the fee is linked to the current allotment price).

Common problems

  • Buying on GPA or agreement. Without HSIIDC's permission, the buyer bears the risk of resumption, even pleading ignorance. EMP-2015 says this plainly.
  • Project deadline. The transferee must finish within the original or extendable time. Clause 5.5 allows no extension beyond the fifth year from allotment or possession, whichever is later.
  • Completion test. Minimum construction is 25% of permissible covered area up to 1 acre, 20% above 1 up to 5 acres, 15% above 5 acres, plus production with plant and machinery worth at least 30% of the value prescribed.
  • Missed PTL deadline. A delay beyond 120 days costs 25% of the normal transfer fee.
  • Transfer without permission. A penalty equal to the normal transfer fee applies.
  • Share deals. Selling 51% of a company counts as transfer, with the same fees.

See also IMT plot: allotment or resale and industrial estate procedures.