Beyond the building
A completed building is not an operating facility. Operations typically need:
- Occupation-stage approval of the building.
- Fire certificate appropriate to the occupancy and stored materials.
- Pollution-control consent to operate, where the activity requires it.
- Sanctioned power load and connection in the occupier's name.
- Water source; HWRA permission if using groundwater.
- Registrations under labour law — the [four Labour Codes](/policies/labour-codes-commencement-2025/) took effect on 21 November 2025.
- Licences for storage of petroleum, explosives, gases or hazardous chemicals where relevant.
- Estate-authority permission for the activity, where the plot is in an estate.
Plan backwards
Work back from the operating date. The slowest item usually sets the schedule.
Governing rule
Checked on 12 Oct 2026. Something changed? Tell us.