Haryana Land Pooling Policy, 2022

Landowners give land to HSVP or HSIIDC voluntarily and get developed plots back. Notified 22 August 2022. A 2026 replacement was approved by Cabinet on 3 November 2026, as reported.

Policy22 Aug 2022

What it governs

Lets a landowner, directly or through a registered aggregator, offer land to a state development body for a project. In return the owner gets a share of the developed plots, worked out from the value of the land given.

What it means for an owner or buyer

  • HSVP handles projects in urbanisable areas of development plans. HSIIDC handles industrial, infrastructure and institutional projects anywhere in Haryana.
  • Once a project is approved, an entry goes into the land records. The Sub-Registrar then needs the agency's prior approval to register any deal on that land.
  • Under the 2022 policy, the owners' share is based on a valuer's estimate of the undeveloped land against total project cost. It is capped at 60% and has a floor of 30% of the equivalent saleable area.
  • Owners get a transferable Land Entitlement Certificate when the sale deed is signed. The agency bears stamp duty and registration fee on that deed.
  • As reported, the 2026 policy fixes the owners' share at 50% of saleable area and sets a 4-year completion deadline.

Key numbers

Clause 13(iii), saleable area norm55% (plus or minus 5%) of total area for residential, industrial or institutional; 35% (plus or minus 3%) for fully commercial
22 Aug 2022
Clause 14(ix), owners' shareMaximum 60%, minimum 30% of equivalent saleable area
22 Aug 2022
Clause 18(i), completion targetAgency to endeavour to complete within 3 years of final approval
22 Aug 2022
Clause 8(i), application windowNot less than 60 days, extendable by up to 30 days
22 Aug 2022