Airport height NOC — when you need one and how to apply on AAI NOCAS

Under GSR 751(E) of 30 Sep 2015, a height NOC is needed within 20 km of a VFR or 56 km of an IFR airport; AAI's NOC is valid 8 years and free.

4 min readChecked on 28 Nov 2026

What it is

Buildings and structures near an airport need a height clearance NOC before construction starts. The rule is the Ministry of Civil Aviation's notification GSR 751(E), notified on 30 September 2015, which replaced the earlier S.O. 84(E). For civil airports, the Airports Authority of India (AAI) issues the NOC through its online system, NOCAS. For defence aerodromes, the defence authorities issue it.

The NOC fixes the permissible top elevation of the structure, in metres above mean sea level (AMSL). The height above ground is that figure minus the site elevation.

When you need it

AAI's FAQ gives the distance test, measured from the Aerodrome Reference Point (ARP) of the nearest airport:

  • Within 20 km of a VFR airport, or within 56 km of an IFR airport: NOC needed.
  • Beyond those distances, with the structure below 150 m above ground: NOC not needed.

NOCAS publishes a list of airports marked IFR or VFR. Measure from the ARP of every airport near the site, not only the nearest one; around Gurugram this includes Delhi's airport. TCP's TOD policy also makes extra FAR subject to AAI height limits. See TOD zone check.

Colour Coded Zoning Maps (CCZM). AAI has prepared CCZMs for major airports. Where a CCZM exists and the proposed top elevation is below the CCZM's permissible elevation, the local body can approve the building without referring to AAI. NOCAS "auto-settles" such cases with a letter that an NOC is not required.

Documents

From AAI's guidelines:

  • Site elevation and coordinates certificate in AAI's standard format, from a surveyor AAI accepts. Coordinates in WGS-84, to 1/10th of a second; position accuracy within 3 m and vertical within 0.5 m. Elevation in metres AMSL or EGM-08, as applicable to the airport.
  • For plots above 300 sq m (approx. 359 sq yd): coordinates and elevation of all corners, plus the point nearest the airport. For 300 sq m or less: at least the nearest point.
  • Undertaking 1A (buildings, chimneys) on Rs 10 non-judicial stamp paper. 1B for transmission lines, 1F for windmills.
  • Authorisation letter if someone other than the owner or lessee applies.
  • Photo ID: voter ID, Aadhaar, PAN or passport.
  • Airport operator's approval, if the site is inside airport premises.

Steps

  1. Check the CCZM first. On NOCAS, open the CCZM for the airport, or use "Check Approximate Permissible Top Elevation" with the site's coordinates. The result is indicative only.
  2. Get the site surveyed. Use a surveyor that AAI accepts: ULB-licensed surveyors, AAI-empanelled surveyors, or airport operators. AAI's guidelines page says Survey of India certificates are not accepted, though one FAQ answer still mentions Survey of India. Follow the guidelines page.
  3. Register on NOCAS with your email ID and photo ID, and activate the account from the email link.
  4. Apply. Choose "Apply NOC", enter coordinates, site elevation and the full top elevation, including water tanks, masts, lightning arresters and vents. Upload scanned PDFs, each under 500 KB. An application cannot be edited after submission.
  5. Track. NOCAS issues an NOC ID. Status shows on the dashboard; rejections come by email or SMS with reasons.
  6. Do not start work before the NOC is issued. AAI's FAQ says this, and the applicant gives an undertaking to that effect.
  7. Review or appeal. If the permitted height is lower than needed, a review can be filed once with the designated officer. An appeal lies to the Appellate Committee set up by MoCA.

Usual time and cost

  • Fee: AAI says there is no fee for applying for or obtaining a height NOC.
  • Validity: 8 years from issue.
  • Appeal fee: Rs 2,00,000 plus GST.
  • Time: AAI's pages do not state a processing time. It depends on the case. We can tell you what to expect for a site on request.

The survey and undertaking costs are separate and depend on the surveyor.

Common problems

  • Data mismatch. The most common rejection: coordinates or elevation in the application do not match the certificate. NOCAS lists this first among reasons for rejection.
  • Wrong datum. Check whether the airport uses EGM-08 or AMSL before the survey.
  • Owner and applicant differ without the authorisation part of Undertaking 1A filled in.
  • Incomplete undertaking. Missing witnesses, signatures or stamp paper.
  • Wrong authority. Sites outside AAI's jurisdiction need an NOC from the State, defence or private operator.
  • Data found wrong later. AAI treats the NOC as void from the start if the real data differs from what was filed.
  • Height lost in design. Rooftop tanks and masts count in the top elevation.

Governing rule

Checked on 28 Nov 2026 against: Ministry of Civil Aviation — Height Restrictions for Safeguarding of Aircraft Operations Rules, 2015 (gazette notification page); Airports Authority of India — NOCAS home; Airports Authority of India — NOCAS FAQs; Airports Authority of India — NOCAS Guidelines for applicants; Airports Authority of India — NOCAS guidelines page. Something changed? Tell us.