What it is
A change of land use (CLU) permission is the Town & Country Planning (TCP) Department's consent to use agricultural land in a controlled area for something else: a warehouse, an industry, a school, a hotel, a farmhouse. It is granted under the Punjab Scheduled Roads and Controlled Areas Act, 1963. A colony licence is a different permission, under the 1975 Act.
The base policy is TCP's memo of 19 December 2006. Two rules from it still decide most cases:
- The CLU must conform to the land use proposals of the development plan and its zoning regulations.
- Where the development plan is published, the Director, Town & Country Planning decides. Where it is not, the Government decides.
On top of this sit use-specific CLU policies (warehouse, industry, hotel, farmhouse and others), listed on TCP's policy index. The 2006 policy also sorts controlled areas into hyper, high, medium and low potential zones. The controlled areas around Gurgaon town are hyper potential, and the other controlled areas in Gurugram district are high potential. The zone sets area norms and charges.
When you need it
- Building anything other than agriculture, or what the zone already permits, on land in a controlled area.
- Buying land sold as "CLU land". Ask for the CLU letter number and date, then check the conditions in it.
- Before a building plan. TCP sanctions the building plan only after the CLU is granted.
Start with the zone. See reading the Gurugram development plan.
Documents
TCP's CLU chart and its 2017 memo list these for scrutiny:
- CLU-I application form, with the scrutiny fee paid.
- Title papers: tatima and mutation, sale deed or lease.
- Aks shajra plan and site plan.
- Survey and land-utilisation plan at 1 inch = 40 feet, showing the existing means of access, certified by the revenue authorities.
- Project report or conceptual plan.
- For a retail fuel outlet, the oil company's LoI. For an MSME, its registration.
- After the LOI: CLU-II compliance form, payment of charges, and the agreement.
Steps
- Check the zone. Read the final development plan and zoning regulations on tcpharyana.gov.in. If the use does not conform, the CLU will not be granted under the normal route.
- Apply online. Applications for an industry or a warehouse are filed on the HEPC portal (Invest Haryana), as the 2017 memo requires. Other CLUs are filed online with the TCP Directorate.
- Scrutiny at TCP Directorate (4 days on TCP's chart). A patwari and a JE check title, shajra, site plan and fee. An incomplete file is returned.
- Site report by the District Town Planner (7 days). The DTP confirms the site, its conformity to the plan, and any existing violation.
- Circle office report by the Senior Town Planner (2 days).
- Examination at the Directorate, recommendation, decision (21 days). The DTCP grants the LOI or rejects, or sends the file to Government where relaxation is needed. The chart totals 37 days to this point.
- LOI compliance. Pay the charges online and submit the CLU-II form and agreement. The chart gives 22 days from compliance to the final CLU letter.
- Building plan. Apply for the building plan once the CLU letter is issued, then build within the time the letter allows.
Usual time and cost
Time. TCP's Right to Service list (service 144) gives 60 days for a CLU in a controlled area inside a final published development plan and a conforming zone, except cases within the Government's competency. The Designated Officer is the Director General, TCP. The internal chart totals 37 days to LOI and 22 days from LOI compliance to CLU. Cases needing Government relaxation are outside the 60-day service.
Cost. Three heads apply:
- Scrutiny fee, at the rate prescribed in the 1963 Act's rules, on the applied area.
- Conversion charges, under Schedule IV of the 1965 Rules. The 2012 schedule for the Gurgaon-Manesar Urban Complex (hyper potential) lists, per sq m: residential Rs 210 on an NH, Rs 158 on a scheduled or sector road, Rs 105 elsewhere; industrial Rs 100; warehouse other than agro produce Rs 150. Check whether TCP has revised these before costing.
- EDC and other charges, where the use-specific policy applies them.
Approx. totals depend on area, use and road frontage. We can work them out for a parcel on request.
Common problems
- Wrong zone. A CLU for a use the zone does not allow needs Government relaxation or a plan amendment.
- Approach road. Each CLU policy sets a minimum approach. A revenue rasta narrower than that fails, even if the land is right.
- Title gaps. Mutation pending, co-owners not joined, or a GPA-only chain. Fix these before applying.
- Restricted land. If any part may be PLPA, forest or Aravalli land, settle that before applying. See Aravalli and forest land check.
- Lapsed CLU. The letter sets conditions and a time to build. A buyer should read the letter itself, not rely on a broker's word.
- Released acquisition land. Some land along the KMP Expressway went to the agriculture zone with no CLU allowed. See warehouse land along KMP.
Governing rule
Checked on 28 Nov 2026 against: Town & Country Planning Dept, Haryana — Policy for grant of licence and CLU, Memo No. 7/16/2006-2TCP, 19.12.2006; Town & Country Planning Dept, Haryana — TCP services under Right to Service, with the CLU process chart; Town & Country Planning Dept, Haryana — Scrutiny of CLU cases filed on HEPC website, Memo No. Misc.447, 10.08.2017; Town & Country Planning Dept, Haryana — Schedule IV conversion charges, notification of 11.09.2012; Town & Country Planning Dept, Haryana — policy index (CLU policy documents). Something changed? Tell us.