What it is

The 135 km KMP (Kundli–Manesar–Palwal) Expressway runs through Gurugram district near Manesar. Land along it is sold for warehousing. Two lines in the Gurugram-Manesar development plan 2031 decide most of these deals:

  • Green belt. The plan reserves the KMP as a 100 m road with a 100 m green belt on both sides. The plan defines a green belt as land along a road meant mainly for future widening or for services.
  • Released acquisition land. In its meeting of 15 February 2011, the Cabinet Sub Committee on Infrastructure decided that land under acquisition by the Industries Department along the KMP would go to the agriculture zone after release, on condition that no CLU or licence is granted, so that it is used only for agriculture.

Outside these, a warehouse in the agriculture zone needs a CLU under TCP's warehousing norms. See the KMP Expressway place page.

When you need it

  • Before paying token money for land sold as "KMP frontage" or "warehouse land".
  • Before signing a lease with a developer who plans to build on such land.
  • When a seller says the land was "released" from acquisition.

Documents

  • Jamabandi, mutation and aks shajra of the khasras.
  • Any acquisition notice or award covering the village, and the release order if the land was released.
  • The GMUC-2031 plan sheet with the khasras placed on it. See reading the Gurugram development plan.
  • Demarcation, to measure the distance from the KMP right of way.
  • Any CLU letter the seller relies on, with number and date.
  • Approach road record: revenue rasta width in the shajra.

Steps

  1. Place the land on the plan. Mark the 100 m KMP road and the 100 m green belt on each side. Land inside the green belt is not available for a warehouse.
  2. Check acquisition history. Ask the Land Acquisition Collector or the Industries Department whether the khasras were under acquisition. If released under the 2011 decision, the plan condition is agriculture only, with no CLU or licence.
  3. Check the zone. If the land is in the agriculture zone and not released land, a warehouse can be considered under TCP's warehousing CLU norms.
  4. Check the warehouse norms. TCP's memo of 5 July 2022 (Annexure-I) sets, for a warehouse in the agriculture zone: minimum 2 acres; FAR 75%; approach 33 ft for agro warehouses and 44 ft for non-agro warehouses; 15% of the site for idle truck parking; setbacks of 6 m (agro) and 9 m (non-agro). Up to 10% of FAR may be used for packaging, assembling or kitting. Sub-division of land is not allowed.
  5. Check other routes. The 2022 memo also sets norms for logistics parks (25 acres, 60 ft approach), warehousing with retail (10 acres), and truckers' parks along NHs (10 acres).
  6. File the CLU on the HEPC portal, as TCP requires for warehouses. See CLU in Haryana.
  7. Check the restrictions overlay. In the Aravalli stretch near Manesar and Sohna, check PLPA and forest status. See Aravalli and forest land check.

Usual time and cost

  • CLU time: TCP's Right to Service list gives 60 days for a CLU within a final published development plan and conforming zone.
  • Conversion charges: the 2012 Schedule IV lists Rs 150 per sq m for warehouses other than agro produce and Rs 100 per sq m for agro warehouses in the GMUC controlled area. Check for later revisions.
  • Policy incentives: the LWR Policy 2019 was extended on 31 January 2025 until a new policy is notified. Any incentive is reimbursed by the Industries Department; TCP recovers its charges in full.

Exact charges depend on area and frontage. We can work them out for a parcel on request.

Common problems

  • "Investment zone" claims. The LWR Policy 2019 says the 2 km stretch on both sides of the KMP "will be declared" an investment zone, and that a "Logistics Zone" will be earmarked along the KMP with new enterprises exempt from CLU. We have not seen a notification earmarking that zone in GMUC. Do not treat the policy line as a CLU.
  • Released land sold as warehouse land. The no-CLU condition sits in the development plan itself.
  • Green belt sold as frontage. The green belt is for road widening and services. It may be acquired later.
  • Narrow rasta. A 22 ft or 33 ft rasta fails the 44 ft norm for a non-agro warehouse.
  • Agro CLU used for non-agro storage. The two carry different conversion charges, setbacks and approach widths. Storage must match the CLU granted.
  • Access. The KMP is access-controlled. Frontage does not mean direct access; check the approach from a sector road or rasta.

Governing rule

Checked on 28 Nov 2026 against: Town & Country Planning Dept, Haryana — FDP 2031 GMUC notification (KMP road reservation, released-land condition, green belt definition); Industries & Commerce Dept, Haryana — Logistics, Warehousing & Retail Policy 2019 (Gazette, 9.3.2019), via Invest Haryana; Industries & Commerce Dept, Haryana — corrigendum extending the LWR Policy, 31.1.2025; Town & Country Planning Dept, Haryana — warehousing and logistics CLU norms, Memo No. Misc-218/2022/7/11/2022-2TCP, 05.07.2022; Town & Country Planning Dept, Haryana — Schedule IV conversion charges, 11.09.2012. Something changed? Tell us.