What it governs
Sets when a residential plot may be built as stilt parking plus four floors, linked to the population density in the approved layout plan. Also raised PDR rates for plots above 250 sqm.
What it means for an owner or buyer
- No new S+4 plan can be approved while the hold lasts. TCP's order of 3 April 2026 put all S+4 approvals on hold and disabled S+4 applications on its S+4 portal and HOBPAS.
- Where allowed, S+4 applies outright only in colonies or sectors whose layout plan is approved at 18 persons per plot.
- In layouts approved at 13.5 persons per plot, S+4 also needs a 10 m or wider road plus either a mutual consent agreement with neighbours or a 1.8 m side setback.
- Registering a fourth floor as a separate unit is governed by a 2019 policy. It requires one-third of the applicable EDC and caps height at 16.5 m.
Key numbers
| Para 1, layout density | S+4 permitted where layout plan approved with density of 18 persons per plot 2 Jul 2024 |
|---|---|
| Para 2, conditional S+4 | 13.5 persons per plot layouts — access from 10 m or wider road and consent or 1.8 m side setback 2 Jul 2024 |
| Para 4(ii), refund of unused PDR on HSVP auctioned plots | Refund with 8% interest if applied within 60 days of the order 2 Jul 2024 |
Amendment timeline
- 7 Mar 2019 — Fourth floor allowed to be registered as a separate dwelling unit on payment of one-third EDC; stilt parking mandatory for new construction; height 16.5 m (Memo No. Misc-149/2019/7/03/2019/2TCP).
- 23 Feb 2023 — All fresh S+4 building plan approvals on residential plots kept in abeyance across TCP, HSIIDC, ULB and HSVP.
- 16 Mar 2023 — Expert Committee constituted to recommend future course of action on S+4.
- 26 Jul 2024 — Further order on approval of S+4 on residential plots (listed on TCP S+4 portal).
- 3 Apr 2026 — TCP directs all S+4 approvals on hold after High Court interim order of 02.04.2026; no layout, zoning or service plans at 18 persons per plot to be approved meanwhile.
Applies to
Licensed colony